Construction Updates 12.18.19

The first phase of our ONE Campaign expansion is well underway. All of the significant water and sewer line work is now complete for this phase and most of the concrete foundations have been poured. Steel framing for the Learning Center and new offices is well underway, and the early stages of demolition of the “point” of the gathering space—which will soon house the Adoration Chapel—has begun. Workers are also putting the finishing touches on the new meeting space roof, with a goal of having this construction “under cover” by the end of the month. Stay tuned for final renderings of our stained glass windows, chapel icons and a new outdoor statue, and pray for the safety and comfort of our workers as colder weather approaches.

 