Construction Update 10.13.19

Things are moving along in our construction project, which means we have some big updates to announce that will affect our current use of campus. Please take a moment to review the exciting projects scheduled for the month of October and resulting campus changes.

On October 14, the removal of stone and wood trim on the existing entrance will begin. This will necessitate the movement of daily Mass to Wellnitz Hall from October 14 through October 25. Beginning October 16, Wednesday School Mass will be held in the MPR through December 1.

On October 19, the new airlock entrance will be available to use for entry into the church on weekends only.

October 21 will bring several exciting changes to our campus. The first delivery of Structural steel will arrive, staged on the concrete slab (section A) inside the construction zone. This means that no parking will be affected. We will begin demolition of the current existing church entrance. However, the new airlock entrance, the deck entrance, and the Davidson Rd entrance will remain open on weekends to allow use of the Church Proper.

October 25 will tentatively see the pouring of slab concrete on sections B&C. This will allow major steel work to happen all through November.

The goal is to have steel erection complete by December 1 so that we can use the new airlock entrance every day to enter the church.

As always, if you have any questions, please direct them to Tom Kollar, business manager at tkollar@stbrendans.net.