Painting and door installation this week!

Yesterday we wiped down the walls, vacuumed the floors, electrical boxes, around windows and the duct  work, primed all walls, constructed and installed steps from the garage to the laundry room, and wrapped the half height porch posts. It was a shortened day, because the primer had not dried sufficiently to start with the paint.
On Wednesday and Saturday this week we plan to continue with the interior painting, trim the porch posts, install cabinets, lay luan, begin painting trim work and hang interior doors, depending upon the experience and number of our volunteers for each day.
Please let Bonnie know by Tuesday morning if you can work on Wednesday, and by Thursday morning if you can work on Saturday.  Don’t forget to bring your own lunch if working on Wednesday.  Lunch will be provided on Saturday.
Thanks for your help!